Current Status
Five stations are complete: Brookhaven, College Park, Inman Park, Kensington, and Oakland City.
West End and Chamblee Stations are in progress. Work has been paused and is anticipated to resume in Summer 2025. Estimated completion is panned for late Fall 2025.
Project Overview
MARTA is making improvements to parking lots at 10 of our stations in the coming years. Besides paving, we’re improving ADA access, crosswalks, sidewalks, adding more ADA parking spaces, upgrading to LED lighting, landscaping and more.
Parking, pedestrian access, and potentially bus access may be affected at the stations listed below while upgrades are made. At this time, we
expect the number of spaces at each station to meet the current needs of our
customers throughout the projects. All stations will have parking
available during repaving.
Please check this page often, as more details will be provided once available. You
may also check the Key Station Parking page for up-to-date information
on parking lot status.
The following parking lots are included in this repaving project:
Red/Gold North Stations
Red/Gold South Line
- College Park
- East Point
- Oakland City
- West End
Blue/Green Line East Line
- East Lake
- Edgewood/Candler Park
- Inman Park/Reynoldstown
- Kensington
Stay Informed
Please take a moment to sign up for
email updates here. You can sign up for all project updates or choose projects by your location and interest.
Contact
For questions/comments about this project, please contact the MARTA Project Manager:
Patrick Permell
Project Manager II
ppermell@itsmarta.com